Tuesday, November 27, 2007

Bridge Opening Delayed Until December 13th...at least

Here is the latest from Mark Miller, P.E.:
According to the contractor, the parapet cover plates are to be shipped late this week and should arrive at the site early next week. Once they are on site, it will take a couple of days to form, pour and strip the parapet sections that need to be completed. It will take a minimum cure time of seven days after the pour before we would be able to open the structure to traffic. This would place opening around the 13th at the earliest.

The good news is that it might be open for Christmas!